technical
butterfly bridge bedfordluton_airportsizewell power station in suffolk
technical documentation
added
20/05/2009
Download

Best Practice - Working Group Co-ordination Guide v1.0

The objective of this procedure is to provide Street Authorities (SA’s) and their teams with a consistent process and schedule for conducting co-ordination/ liaison meetings with Statutory Undertakers (SU’s) and other interested parties. 

added
20/05/2009
Download

Best Practice - Working Group Performance Information Process v1.0

The objective of this process is to provide a standard format for presentation of Statutory Undertakers (SU’s) and Highway Authorities (HA’s) NRSWA/TMA performance data in the Anglian HAUC (AHAUC) area, and to establish a standard procedure to be used by all members of AHAUC.

added
20/05/2009
Download

Best Practice - Working Group Recycling Protocol Part 1 - Use of Hydraulically Bound Material (HBM) v1.0

This document is designed to provide a formal process for both the Highways Authorities (HAs), Statutory Undertakers (SUs), and other interested parties to follow when using Hydraulically Bound Materials (HBM) within the Anglian HAUC area.

added
20/05/2009
Download

Best Practice - Working Group Dispute Resolution v1.0

This document is designed to provide a formal process for both Highway Authorities (HAs) and Statutory Undertakers (SUs) to follow when they are found to be in disagreement with regards to street works matters within the Anglian HAUC area.

added
20/05/2009
Download

Best Practice - Working Group Coring Protocol v1.0

This document is designed to provide a formal process for both Highway Authorities (HAs) and Statutory Undertakers (SUs) to follow when undertaking any core sampling, associated analysis and reporting in the Anglian HAUC area.

added
16/04/2010
Download

AJAG - Regional Scaffold Permit